Entegris
Project Description:
This project was delivered on a Design / Build basis, with a fast track focus due to client requirements. Entegris & SPEC have enjoyed a successful project with schedule and budget targets obtained.
Project Highlights Include:
- Contract Basis Design / Build Open Book
- Contract Value $12 Million
- Total Building Size 200,000 SF
- SPEC Area Renovated 109,000 SF
- SPEC Area Built – Out From Shell 41,000 SF
- Total Area Renovated 150,000 SF
Schedule Highlights:
- Start Design February 1, 2002
- Demolition Starts May 1, 2002
- Construction Starts June 1, 2002
- Phase I MFG First Move In August 19, 2002
- Phase I MFG Move In Complete September 30, 2002
- Phase II Laboratories Complete December 15, 2002
Key Scope Features:
- Conversion of Existing Class 10,000 Clean Rooms to Class 1000
- Significant Utilities and Power Installed to Ceiling Mounted “Patch Panels”
- 75 GPM RODI System with Trending System
- Full Service Kitchen and Cafeteria
- 50 HZ Power Converter and Distribution
- Upgraded Base Building HVAC Plant
Engage SPEC in your Microelectronics Project
Related Projects:
Working With SPEC
To engage SPEC on your project, please select from the options below:
- Starting a New Project
- Upgrades/Repairs to Existing Facilities
- Buying a Product from SPEC