Entegris

Entegris

Project Description:

This project was delivered on a Design / Build basis, with a fast track focus due to client requirements. Entegris & SPEC have enjoyed a successful project with schedule and budget targets obtained.

Project Highlights Include:

  • Contract Basis Design / Build Open Book
  • Contract Value $12 Million
  • Total Building Size 200,000 SF
  • SPEC Area Renovated 109,000 SF
  • SPEC Area Built – Out From Shell 41,000 SF
  • Total Area Renovated 150,000 SF

Schedule Highlights:

  • Start Design February 1, 2002
  • Demolition Starts May 1, 2002
  • Construction Starts June 1, 2002
  • Phase I MFG First Move In August 19, 2002
  • Phase I MFG Move In Complete September 30, 2002
  • Phase II Laboratories Complete December 15, 2002

Key Scope Features:

  • Conversion of Existing Class 10,000 Clean Rooms to Class 1000
  • Significant Utilities and Power Installed to Ceiling Mounted “Patch Panels”
  • 75 GPM RODI System with Trending System
  • Full Service Kitchen and Cafeteria
  • 50 HZ Power Converter and Distribution
  • Upgraded Base Building HVAC Plant

Engage Engage SPEC in your Microelectronics Project

Related Projects:

ASTeXASTeX
SPEC provided a Design/Build/Commissioning package to ASTeX, for the relocation of their combined Manufacturing, R&D and Office Space from their old facility in Woburn MA to the expanded facility... more

 

Subscribe to SPEC's email list: