Project Description:
Konarka, a fast growing photovoltaic company out of Lowell, MA, decided to modify their process and change their base solvent to a chlorinated constituent that required water scrubbing downstream of their existing thermal oxidizer. To address this new requirement they purchased a new thermal oxidizer from Durr, a leading supplier of industrial cleaning and filtration systems, with a downstream scrubber that was designed to handle the new solvent. After the purchase, Konarka realized that they needed help with the installation of the new unit and contacted SPEC. SPEC immediately set up a conference call with both Konarka and Durr to quickly identify the project requirements and timeline. SPEC’s experience installing similar thermal oxidizers at other clients’ sites made us an excellent partner for Konarka on this project.
The project consisted of satisfying a list of installation requirements provided by Durr to Konarka, which ultimately provided the contractual basis for SPEC’s scope of work. SPEC ensured that all of the required infrastructure: power, utilities, structural concrete pad, site work, etc. were designed and installed to meet Massachusetts code and satisfy the unit’s requirements. The timetable for this project was particularly important since the unit was expected to ship in June, with all installation requirements completed by its arrival at Konarka’s facility, and start up in July 2009. SPEC had less than three months to help Konarka prepare for the thermal oxidizer delivery and installation.
Project Highlights:
- Permitting – SPEC’s engineering staff provided stamped drawings for submittal for a building permit required for the concrete pad. SPEC’s construction team worked with the Fire Department and the Building Inspector to obtain the proper permits and ensured that all design requirements were met. They also followed up with the local authorities at the end of the project to close out the permits.
- Schedule – The project execution was accelerated because SPEC was brought on after the product had been ordered. In order to meet the tight schedule, SPEC prepared permit level drawings to submit to the town for approval prior to final construction drawings being completed. This allowed us to obtain the permit and subcontract the site and concrete scope early so that we could have the pad poured and cured in time for the arrival of the equipment.
Engage SPEC for your Alternative Energy Project
Related Projects:
Confidential Client - Cellulosic Ethanol Plant
The client initially contracted SPEC to provide process engineering expertise for their fermentation... more
Qteros (Formerly SunEthanol)
A venture capital funded Cellulosic Ethanol company growing out of small lab space located near the ... more
St. Gobain
A global technology company had developed a solid oxide fuel cell (SOFC) ceramic fuel cell technolog... more
Featured Projects
Antigenics, LLC
SPEC successfully designed, constructed and commissioned a 30,000 square-foot Pilot-Scale manufactur... more
Arkwright
SPEC has designed, constructed and performance tested a 5000 square foot, $4.7M, specialty coatings ... more
Aspen Aerogels
This Design/Build project was delivered on a Guaranteed Maximum Price (GMP) contract. SPEC involveme... more
ASTeX
SPEC provided a Design / Build / Commissioning package to ASTeX, for the relocation of their combine... more
AstraZeneca (Air Dryer)
SPEC worked with Donovan Engineering and Construction as a design-build team to install a new Air Dr... more
AstraZeneca (Methanol)
SPEC worked with Donovan Engineering and Construction as a contracting team to install a new methano... more
Cabot
SPEC has provided a Design / Build package for this new manufacturing facility. The project schedule... more
Central Artery
SPEC has successfully completed the first phase of this ongoing project with the commissioning of th... more
Confidential Client - Cellulosic Ethanol Plant
The client initially contracted SPEC to provide process engineering expertise for their fermentation... more
DSM NeoSol
Delivered on a Design/Build basis, this project involved the relocation, upgrade and startup of DSM ... more
E Ink
The client contacted SPEC to work with them in expanding one of their downstream process manufacturi... more
Entegris
This project was delivered on a Design / Build basis, with a fast track focus due to client requirem... more
IntelliSense
SPEC provided a Design / Build package for IntelliSense Corporation for the design, construction and... more
Johnson Matthey
SPEC has supported Pharm Eco Labs (now Johnson Matthey Pharmaceuticals Services), dating back to 199... more
Qteros (Formerly SunEthanol)
A venture capital funded Cellulosic Ethanol company growing out of small lab space located near the ... more
St. Gobain
A global technology company had developed a solid oxide fuel cell (SOFC) ceramic fuel cell technolog... more